TRANSPORTATION AND HANDLING OF WIND TURBINES FOR THE CUU AN WIND POWER PLANT | 46.2 MW
CUU AN WIND POWER PLANT PROJECT | 46.2 MW
- Project Name: Cuu An Wind Power Plant
- Project Owner: Cuu An Wind Power Joint Stock Company
- Capacity: 46.2 MW
- Location: Gia Lai
- Duration: 4 months
- Specifications:
- Turbine type: Envision - En3.X/156 WTG
- Wind turbine blade: 76,8 m
- Heaviest type of cargo: Tower 1: 89 tons
- The widest and tallest type of cargo: Tower 1: Ø4,6 m
Scope of work:
- Receive goods at the port, carry out customs clearance procedures, and handle the delivery of the goods;
- Receiving, transporting, and loading/unloading cargo to/from a temporary storage area at the port;
- Transporting equipment from the temporary storage area to the project site;
- Carry out the lifting and lowering of equipment from the transport vehicle to the turbine pedestal location.