MJC NOT ONLY TRANSPORTS AND INSTALLS TRANSFORMERS, UTILITY POLES, AND POWER LINES NATIONWIDE, BUT ALSO EXTENDS ITS OPERATIONS TO OTHER COUNTRIES IN THE REGION
Benefiting from the trust and cooperation of clients such as Power Transmission Companies, as well as suppliers including Dong Anh Electrical Equipment Corporation (EEMC), Cam Pha Electrical Equipment Joint Stock Company (VEE), and ABB Ltd. (a subsidiary of the global ABB Group, with Swiss-Swedish origins), MJC has:
+ Participate in the installation of high-voltage pylons in challenging locations for the Circuit 3 projects: Quang Trach - Pho Noi, Lao Cai - Vinh Yen.
+ Transporting, lifting and installing transformers for transformer stations from 110kV to 500kV such as: Hiep Hoa 500kV Station, Thuong Tin 500kV Station, Lai Chau 500kV Station; 220kV stations: Xuan Mai, Van Tri, Thai Thuy, Can Tho, Tra Noc, Vinh Yen, Ha Dong, Bac Ninh 2, Bac Ninh 3, Ha Giang, Tuyen Quang, Viet Tri...; 110kV transformer stations belong to the high voltage system in the North, Central and South...

Receiving the transformer main body at Dong Anh Electrical Equipment Corporation (EEMC)

Transporting the 220kV-250MVA transformer for Thai Binh 2 Thermal Power Plant.


Transportation and handling of an 80.5-ton reactor using a modular trailer (Hiep Hoa 500kV Substation)

Provided customs clearance, transportation, and loading/unloading services for a 63MVA transformer, moving it from Cam Pha (Quang Ninh) to Shenyang (China) to support a project involving the manufacturing and short-circuit testing of a 110kV-63MVA transformer.


Handling the receipt of a 220kV-250MVA transformer from a sea vessel, completing customs clearance procedures, managing its multimodal transport from Hon La Port (Vietnam), and installing it at the Savan 1 Wind Power Plant in Savannakhet, Lao PDR.


Transportation of a 132-ton, 220kV-250MVA transformer via a combined road and waterway route



Combining multimodal transport



Manual transport, lifting, and repositioning of transformers