TRANSPORTATION AND HANDLING OF WIND TURBINES FOR THE CHO LONG WIND POWER PLANT | 155 MW
- Project Name: Cho Long Wind Power Plant
- Project Owner: Cho Long Wind Power Joint Stock Company
- Capacity: 155 MW
- Location: Gia Lai
- Duration: 3 months
- Specifications:
- Turbine type: Envision - En3.X/156 WTG
- Longest item type: Blade: 76 m
- Heaviest type of cargo: Drivetrain: 103 tons
- The widest and tallest type of cargo: Tower 1: Ø5,6 m
- Scope of work:
- Receive goods from Quy Nhon Port and transport them to a temporary storage yard;
- Transporting equipment from the temporary storage area to the project site;
- Carry out the lifting and lowering of equipment from the transport vehicle to the turbine pedestal location.