TRANSPORTATION AND HANDLING OF WIND TURBINES FOR THE SONG AN WIND POWER PLANT | 46.2 MW

TRANSPORTATION AND HANDLING OF WIND TURBINES FOR THE SONG AN WIND POWER PLANT | 46.2 MW

By 01 tháng 01, 2022 - 16:03 (GMT +07)

SONG AN WIND POWER PLANT PROJECT | 46.2 MW  

  • Project name: Song An Wind Power Plant 
  • Investor: Song An Wind Power Joint Stock Company
  • Capacity: 46.2 MW
  • Location: Gia Lai
  • Duration: 6 months
  • Specifications:

 - Turbine type: CRRC - 3.3MWD160H140

 - Longest type of cargo: Blade: 78,5 m  

 - Heaviest type of cargo: Tower 1: 119 tons  

 - The widest and tallest type of cargo: Tower 1: Ø4,9 m  

Scope of work:

  • Receive goods at the port, carry out customs clearance procedures, and handle the delivery of the goods;
  • Receiving, transporting, and loading/unloading cargo to/from a temporary storage area at the port;
  • Transporting equipment from the temporary storage area to the project site;
  • Carry out the lifting and lowering of equipment from the transport vehicle to the turbine pedestal location.  